MAGA : Shortage of windows
    • 63% of projects under construction report a delay in construction due to a shortage of windows
    • normally the execution of an order for windows took 2-3 weeks, now it is 4-15 weeks, and for some products 20-45 weeks (almost a year)
    • one of the bottlenecks is glass production, therefore, in addition to windows, the crisis also affected products such as dishes, lamps, doors, shower partitions, etc.
    • there is a shortage of resin, which is used for the production of vinyl in some types of window frames, where the waiting time for an order can be up to 45 weeks
    • an attempt to replace stuff with other materials stumbles upon a shortage of aluminum
    • there is also a shortage of insulation, roofing materials, electrical wiring, etc.
    • the cost of building a single-family home increased by 11.8% compared to September 2020 and by 17.6% compared to September 2019, this is the fastest growth in prices since 1979
    • prices on the market at the same time increased by 18.7% over the year (median price - $ 408K), but sales at the same time are falling - new homes sold by 18% less than in the same month a year ago, the market is extremely sluggish